Façade innovation: prefabricated brickwork makes the construction process more efficient
Text Eva GoossensImage Furnibo – Philippe Van Gelooven

“Industrialising construction is becoming essential”
As an innovative business unit within Furnibo, GUST is fully committed to prefabricated brick façades for larger, more complex projects. Its ambition is clear: to make the construction process smarter and more efficient. CEO Steven Maeyaert sees industrialisation as a necessary step. “In traditional bricklaying, a brick is handled up to five times before it is finally laid. That is inefficient, especially when skilled workers are in short supply and expensive.”
This realisation marked the starting point for an intensive R&D programme at Furnibo some six years ago. The system was fully developed through internal projects. Since this year, the solution has also been used on external projects under the name GUST, delivered by contractors other than Furnibo, and the business is steadily expanding.

Prefabricated brickwork: efficiency from the outset
GUST’s core offering is the off-site production of façade elements in a controlled environment. The elements are then delivered to site just in time and installed. This saves a considerable amount of time. According to Martijn Verhelst, BU Manager at GUST, the added value lies in combining preparation and execution: “Everything is prepared digitally and modelled in BIM. Each element is given a unique code, allowing installation on site to be monitored and carried out efficiently. As well as speed, with up to 120 square metres of façade brickwork installed per day at times, this approach also means fewer defects and less reliance on weather conditions. And importantly, the building is made wind- and watertight sooner, so interior finishing can start earlier too. The site is also easier to manage, with fewer material movements and less disruption to the surrounding area.” Brickwork, reimagined and made far more efficient.
Architectural freedom
Does prefabrication restrict the design? Steven Maeyaert, CEO of Furnibo, says: “Even complex façades can be perfectly realised using prefabrication.” One example is O’Sea phase 3 in Ostend, a large-scale residential building developed by Immobel and built by MBG. For this project, prefabricated brickwork in horizontal and vertical bond was used on a beam-and-column structure, covering a total of around 1,600 square metres of façade brickwork. By constructing the façade from prefabricated elements, the brickwork could be completed more quickly and under greater control, with a clear reduction in site risks and weather delays. This is a particular advantage on the coast, where weather conditions still play a major role.
Project details
Project: O’Sea phase 3
Location: Ostend
Architect: Conix RDBM Architects
Client: Immobel
Contractor: MBG

Complete façade service
The potential of prefabrication for architectural expression is even more evident at De Speurder student accommodation in Ghent. This five-storey project with 81 units was developed by ION and built by Furnibo. Around 1,250 square metres of façade brickwork were completed, with GUST providing a complete façade service. The design uses staggered brickwork to create a dynamic façade. Prefabricating the brickwork also made it possible to install the façade without scaffolding, another advantage over traditional bricklaying. Here too, architectural expression is perfectly reconciled with speed and certainty of execution. It is an approach that aligns design and construction seamlessly.

Project details
Project: De Speurder
Location: Ghent
Architect: A154 architecten
Client: ION
Contractor: Furnibo
Question about this story? Ask your question