A new lease of life for the brewery

The area around Gare de l’Ouest in Molenbeek-Saint-Jean is undergoing major change. The regeneration of the whole neighbourhood got under way on the former Vandenheuvel brewery site, which has been impressively redeveloped with numerous new buildings. The latest project is ‘Go West’, a strikingly dynamic development comprising 31 apartments, a shop and a nursery. Its clean, distinctive architecture, combined with a play of white and grey lines, brings a fresh touch that sets it apart in the neighbourhood.
‘Go West’ is part of the ‘Ekla’ redevelopment programme, named after one of Vandenheuvel’s beers. After the brewery closed in the 1970s, the site lay abandoned for decades. In 2013, Revive, a specialist in the redevelopment of brownfield sites, bought the block to deliver the ‘Ekla’ redevelopment programme: a 22 000 m² project comprising a hotel, shops, offices, a primary school, student accommodation and open-market housing. citydev.brussels, the leading public property developer in Brussels, joined the project and bought part of the site (around 1400 m²) for the ‘Go West’ project. The public authority launched a design-and-build tender, which was awarded to architecture practice A2M and developer Ciril (part of the Democo group).

A mix of uses
Construction of a brand-new building began in 2018, with a green space to be created alongside it at a later date. To create a sense of dynamism, the architects devised a concept in which the above-ground height varies from three to six storeys. This provides just over 3800 m² of usable floor area. In addition to a nursery for 36 children and a 45 m² retail unit, 31 conventional apartments with two, three or four bedrooms have been built. Although the interior finish was kept to a standard specification, quality was not compromised. An additional basement level contains plant rooms and a 740 m² car park.
Angled façade
The building has a base with a dark brown brick-clad façade. The upper floors are distinguished by a linear pattern of white and grey render on the front. “The prefabricated balconies have added another dimension to the rear façade, with their high-quality metal cladding,” explains Francis Heeb, project manager at Democo, the construction company that acted as main contractor for the project. “On the Chaussée de Ninove side, the architects designed a very distinctive angled façade, clad in metal cassettes that are slightly offset on each floor. This interesting architectural choice gives the building a particularly dynamic appearance.”

Unforeseen obstacles
‘Go West’ was built to the passive standard, with 30% of the apartments even being energy-neutral. “We achieved this ambition by combining high insulation values, well-designed construction junctions, a very high level of airtightness, communal heating, photovoltaic panels and a combined heat and power system to recover energy,” explains Francis Heeb. “However, achieving this ambition was not the main challenge. The biggest difficulties arose at the initial stage. The site proved to be relatively contaminated and also contained numerous old foundations as well as a huge reinforced-concrete slab. This naturally meant unplanned excavation work to remediate the site, resulting in a great deal of extra work and consequently delays to the construction programme. Fortunately, citydev.brussels responded appropriately by making the necessary funds available to overcome this obstacle. In construction terms, the ‘twisted’ façade proved a technical tour de force, both in terms of stability and finishing. Although we had our work cut out for us at times, the result lives up to expectations. We delivered a very strong performance in terms of quality and programme. We also achieved very good results for airtightness, the number of outstanding items at final handover, less than one per apartment, and overall client satisfaction. ‘Go West’ demonstrates that good cooperation with a funding authority and excellent preparation really do add significant value.” “

The start of a wider regeneration effort
Benjamin Cadranel, managing director of citydev.brussels, is also very pleased with the result. “‘Go West’ is a very high-quality project on a very complex site, and both the architects and the construction company deserve praise. A strong partnership is needed to take on this kind of challenge. Go West is a foretaste of the immense challenges that lie ahead for us in the Gare de l’Ouest area. The Brussels Government has tasked citydev.brussels with coordinating the regeneration of this area. Over the coming years, we will work to transform this brownfield into an attractive, mixed-use neighbourhood that provides jobs, services and facilities, while retaining an offer of high-quality, affordable housing.”
Smeets Laswerken: Aluminium cladding and glass and steel balustrades
The architectural character of Go West is also due in part to the expertise of Smeets Laswerken (Hechtel-Eksel). This decorative metalwork specialist for the construction sector made a major contribution to the building’s appearance. “We were tasked with bringing the projecting terraces and the sloping façade together as a unified whole,” explains managing director Wouter Smeets. “More specifically, we supplied the aluminium cladding and the glass and steel balustrades. The façade’s configuration made this far from straightforward. We therefore carried out a 3D scan first, which we then converted into a precise construction drawing. The result is that the columns and glass balustrades align perfectly with the twists in the façade.” Once again, Smeets Laswerken demonstrated its versatility on this project. “Our work ranges from metal staircases and ramps to balustrades and aluminium façade cladding,” continues Wouter Smeets. “Go West gave us the opportunity to showcase several aspects of our expertise. It is a fine addition to our long list of references, comprising a diverse range of projects throughout Belgium.”
Project details
Client
Ciril (Brussels)
Contracting authority
citydev.brussels (Brussels)
Architect
A2M Architects (Brussels)
Main contractor
Democo (Brussels)